Tuesday, May 29, 2007

How I Spent My Vacation


Painting closet doors ~


~ and more closet doors, and salvaged window and door trim

OK, in truth, I painted only some of these doors. Mike painted the others and the trim pieces. But I painted salvaged bedroom, bathroom, and pantry doors at home, too! Three down - one in progress - three to go.

Wednesday, May 23, 2007

Apartment 2 Panorama View


This patchwork photo of Apartment 2 was taken from the northwest corner. Try to ignore the piles of door and window trim in the middle of the floor and just notice how the light has improved the view. Compare the top photo with the one taken a few days ago, before the plywood was removed.


Gloomy, huh?

So on Wednesday Morning …

… these two guys were already busy when I arrived at the building.



When I went inside, WOW!



It wasn't long before there was light in every room. All the windows were uncovered except three in the front, and they'll appear soon.

Monday, May 21, 2007

Busy Monday



The paint remover is working so much better this spring than it did last fall. The work has barely started, but you can see lots of brick in the area that has been washed.

Disposal of the rinse water requires a little extra care. If you've driven by, you've noticed the orange safety fence. Inside the fence is a big lagoon made from sheet plastic and sand bags. It contains the rinse water until it can be be collected in this huge vacuum tank. The tank is drained into the sanitary sewer so the chemicals can be treated before the water is discharged. If we let it go directly into the storm drain on the corner, the water wouldn't be treated and the chemicals would just flow right through.

Saturday, May 19, 2007

Saturday Night 7:00

What a difference a day makes!


~ for reference, this is Apartment 1


Apartment 1 view 1; the entry hall with closet and powder room on the left


Apatrment 1 view 2; the kitchen as seen from the southeast corner


Apartment 1 view 3; the kitchen as seen from the northeast corner


~ and this is Apartment 2


Apartment 2 view 2; looking into the main living area from the entry hall


Apartment 2 view 5; looking toward the entry hall

Thursday, May 17, 2007

Drywall Coming Up!



First thing on Thursday morning, there is was. Stacks and stacks of the stuff.


When I left at 9:00, this was the scene.

Wednesday, May 16, 2007

Keep your eyes open

People in Washington have noticed that there are more openings on the second floor.



"Why?" they ask.



The simple answer is that we'll need a light source in each room when the drywall is installed, and we think/hope it's starting this week.

"Why don't you just take down all the plywood?" We need to wait until we can coordinate the removal of the plywood and the installation of the repaired window sashes. It's just a matter of (a brief) time before all the plywood will be gone!

Thursday, May 10, 2007

Friday, May 04, 2007

Friday Update

The picture tells the story. I won't say they actually got in each other's way, but there were FOUR crews at work on the building today.



Up in the apartments, Zager Plumbing was finishing the last bits of plumbing, and the plumbing inspector stopped by to see how it looked. Bob and Bill got an A +!

Higher up, in the apartment attics, Johnson Controls was working hard to finish the apartments' ductwork and return air vents.

The crew from Apex Construction returned today and wrapped up several small jobs - leveled one entry floor, added framing for the doorway arches in Apartment 2, and framed the kitchen walls and half walls.

Everyone working in the apartments is hurrying to finish their particular piece of the job before the drywall guys come in next week.

Meanwhile, down in the back basement, the concrete cutters from Iowa Bridge and Culvert were making a terrible racket with a concrete saw and a jack hammer. They're removing the existing concrete floor to permit construction of an exit hallway and restrooms with adequate headroom. More photos later when they're finished.